Hours logged is not a metric: ask your dev vendor this instead
A dev team told me they spent 320 hours last sprint. I asked what shipped, and what evidence they had that they used AI. They didn't know what I meant.
I was on the phone with a dev team recently.
They told me they'd spent 320 hours over the past sprint. And they'd moved the ball about this much.
So I asked the obvious question.
But what did you ship in the past two weeks?
What's done? What's going to be done next sprint?
They said, "No, this is a six-week sprint to get everything done."
Hours are an input
Hours tell you what you paid for. They don't tell you what you got.
A few years ago, hours were a rough stand-in for output, because a developer typing code was the main way code got made. More hours, more code, more features. Roughly.
That link is broken now. With AI doing a lot of the typing, a team still leading with hours is telling you they're measured on effort.
The question that stopped the call
My next question was this:
How much did you leverage AI?
And they said, "I don't know what you mean."
So I put it another way. What's the evidence that you used AI this week?
Everybody has Claude or Copilot. They're using it. So show me. A pull request an agent opened. A test suite the AI generated. A spec that went in and a feature that came out the same day.
What it looks like when it's working
You and I both know I can tell Claude, "go build this," and then go call my mom for a half an hour.
It should be done in a half an hour.
That's the bar now. Plenty of tasks still need a human the whole way through. But a team using AI well leaves a trail of handoffs like that. You can see it in the repo. You can see it in the release notes.
If your vendor can't show you that trail, they're either not using AI, or they're using it and still billing you as if they weren't. Neither one is great news.
What to ask your dev vendor
Next time you get a status report, skip the hours and ask:
- What shipped? Released to users, not "in progress."
- What's the evidence you used AI this sprint? Ask for one concrete example.
- What took longer than it should have, and why?
- What would you do differently if you were paid per outcome?
That last one is fun. Watch how they answer it.
A good team lights up at that question. A team that is selling hours gets quiet, then tells you why outcomes are hard to measure in their line of work.
Change what you measure
If you're the CEO, the fix starts with you. As long as you accept hours as the scoreboard, that's what you'll get.
Ask for releases. Ask for cycle time from request to production. Ask for the AI evidence every sprint until it shows up without asking.
Hours in. Releases out. Measure the second one.
I review outside dev teams as part of my fractional CTO work. If your vendor's reports are all hours and no shipping, book a call at bry.net.
What's on the first line of your dev team's last status report?